Sample project · Live demo

Meridian Residential Tower

London, UK · 9-Storey Residential Tower — Concrete Frame

This is a real CPM schedule computed by Algradia's scheduling engine, mid-project: site works are done, the frame is going up, and excavation finished late — watch the orange and red forecast bars show exactly how that delay ripples through the critical path. Zoom, drag the timeline, collapse phases, toggle Baseline vs Forecast. When you upload your own drawings, this is what you get back in about two minutes.

Critical path: 18 tasks·Project end: 2027-08-19·Total duration: 504 working days
9-Storey Residential Tower — Concrete Frame · Baseline: 2025-09-13 · 504 working days
Day 7
BASELINE
COMPLETE
IN PROGRESS
FORECAST
FORECAST CRITICAL
PHASE / TASK
1Site Preparation
Site mobilization & hoarding
Survey & setting out
Bulk excavation & dewatering
2Substructure
Piling & pile caps
Raft foundation pour
Basement walls & waterproofing
Substructure complete
3Superstructure
1/3
Ground floor slab & columns
Typical floors 1–8 (RC cycle)
12
Roof slab & parapets
Structural top-out
4Facade & Envelope
Blockwork external walls
Windows & curtain wall
External paint & cladding
5MEP Rough-In
0/3
In-slab conduits & sleeves
8
MEP risers & shafts
First fix (electrical & plumbing)
6Internal Finishes
Internal plaster & screed
Tiling & joinery
Second fix & fittings
Internal paint & final finishes
7Testing & Handover
Testing & commissioning
Snagging & authority inspections
Handover
TODAY · 5 Jul
113 Sep
820 Sep
1527 Sep
224 Oct
2911 Oct
3618 Oct
4325 Oct
501 Nov
578 Nov
6415 Nov
7122 Nov
7829 Nov
856 Dec
9213 Dec
9920 Dec
10627 Dec
1133 Jan
12010 Jan
12717 Jan
13424 Jan
14131 Jan
1487 Feb
15514 Feb
16221 Feb
16928 Feb
1767 Mar
18314 Mar
19021 Mar
19728 Mar
2044 Apr
21111 Apr
21818 Apr
22525 Apr
2322 May
2399 May
24616 May
25323 May
26030 May
2676 Jun
27413 Jun
28120 Jun
28827 Jun
2954 Jul
30211 Jul
30918 Jul
31625 Jul
3231 Aug
3308 Aug
33715 Aug
34422 Aug
35129 Aug
3585 Sep
36512 Sep
37219 Sep
37926 Sep
3863 Oct
39310 Oct
40017 Oct
40724 Oct
41431 Oct
4217 Nov
42814 Nov
43521 Nov
44228 Nov
4495 Dec
45612 Dec
46319 Dec
47026 Dec
4772 Jan
4849 Jan
49116 Jan
49823 Jan
50530 Jan
5126 Feb
51913 Feb
52620 Feb
53327 Feb
5406 Mar
54713 Mar
55420 Mar
56127 Mar
5683 Apr
57510 Apr
58217 Apr
58924 Apr
5961 May
6038 May
61015 May
61722 May
62429 May
6315 Jun
63812 Jun
64519 Jun
65226 Jun
6593 Jul
66610 Jul
67317 Jul
68024 Jul
68731 Jul
6947 Aug
70114 Aug
Now try it with your own drawings
Upload your architectural and structural drawings and get a schedule like this one for your project — free, no signup needed. One trial schedule per visitor.